Please visit this site occasionally for more information on all construction activity in Wailea. WCA will be updating this construction page on all activities, including blasting schedules, etc.

If you have any questions about construction activity in Wailea, please contact Larry Clark at design@wcamaui.com.

Construction Info


Fiber-Optic Cable Work - Fiber-optic lines are being installed on Maui for the Department of Hawaiian Homelands. Over the past few months Henkels & McCoy has been working on Piilani Highway and also Honopiilani Highway near Maalaea.

They are now beginning their connection phase from Makena to the Piilani Highway section previously installed north of Maui Meadows. The contractor has been very cooperative with the community by scheduling this phase during the summer months as requested by WCA and providing us with details of the work and a schedule. Beginning the week of April 28, 2008 they will be on Makena Alanui just south of the entrance to the Gold & Emerald Golf Courses. Work will progress north arriving at Kaukahi Street approximately May 23rd, Ike Drive/Alanui on June 13th, and Piilani Highway/Ike Drive on July 14th. Traffic will be minimally impacted by the work as it will impact the northbound and eastbound outer lanes.


Updates

Renaissance/Bacarrat - General Schedule/Construction Issues - WCA has worked with the developer and contractor to work out some of the construction issues and minimize the impacts to the community. There will be many challenges that will be continuously worked on with the neighbors and the community. We believe much can be resolved with communication.

  1. The last day for the Renaissance Wailea was September 6, 2007
  2. The project is scheduled to be completed in November 2010 (32 months).
  3. Liquidation of the furniture and equipment was completed in October.
  4. Abatement started in October 2007. The hotel has the normal asbestos and lead paint removal requirements common to buildings of this age that need to be contained and removed per federal regulations. An independent consultant will be monitoring the air quality to assure that the interests of the neighborhood are ensured.
  5. The interests of Maluhia, and that of conservation, will be addressed by relocating as much of the vegetation as reasonable to north side of the property adjacent to Maluhia. This will provide a noise and visual barrier and provide a nusery for the reuse of the material as landscaping needs are presented.
  6. The schedule has been developed with respect to “in season” issues and the start of major demolition will begin after the winter season, for owners, and rainy months, for environment.
  7. The existing Monkey Pods at the front of the property along Alanui will be carefully removed to provide access and will eventually be replanted at the later stages of construction.

  8. Ulua/Mokapu Beach Park Improvements will occur in early 2009 in conjunction with the Baccarat development. The improvements will include 22 additional parking spaces and resurfacing the driveways, along with improvements to the drop-off area, showers and landscaping coordinated by WCA. The improvements will be phased to allow the public to use the park during construction.
  9. The Mokapu Beach pathway and boardwalk will be open during construction.


Other Construction

  1. The MF-19 site below the water tank adjacent to Diamond Resort is underway. It consists of grading and infrastructure work for 9 homesites. The grading is completed and final utility lines are awaiting permits.
  2. MF-11 which is the 12 home sites surrounding the Gateway Center at the top of Ike Drive is completed.
  3. The Gateway Center grading is complete and verticle construction is slated to begin in July 2008.
  4. MF-7 at the corner of Alanui and Okolani has been approved by the County and is scheduled to begin late 2008 pending building permits. The site is considered "balanced" which means the need for fill is equal to the need to excavate. This equates to very minimal truck traffic from the project. More information will be available as construction nears.

Please feel free to contact our office for informaton on any of these projects.